Here are some of the details for the 2009 Aerial Photography Acquisition project that includes 1 meter color NAIP imagery for some portions of Utah and smaller areas where 6 inch photography will be collected for agencies providing partnering funding for specific areas at a higher resolution imagery. Click on the map to view a more detailed representation of the acqusition areas.
Acquisition Plan Details:
Spring acquisition March-April, leaf off and no snow (Exception: Cache will be acquired in the fall)
Final delivery no later than September 30, 2009
25cm resolution (1 foot), 3 band natural color, 4327 total square miles (to be included and distributed as part of the State Geographic Information Database
810 square miles of this will be collected as 12.5cm (6 inch). These products will be owned by partnering organization but will be resampled to 25cm for inclusion in the SGID
Control from 2006 will be reused and any additional control needed will be collected by the vendor
QA/QC will be performed by the USGS and partners
Partnering agencies for NAIP 2009 (1 meter - 3 band natural color):
BLM – contributed money to acquire complete state
Cost sharing parties for NAIP acquisition and delivery fees ($29,111)
SITLA
Public Lands and Policy Coordination Office (PLPCO)
Utah Department of Agriculture
AGRC
Division of Natural Resources (DNR)
Forestry, Fire and State Land
Utah Geological Survey
Oil, Gas and Mining
Parks and Recreation Department
Division of Water Rights
Division of Water Resources
Division of Wildlife Resources
Partnering agencies for HRO 2009 (12.5 and 25 cm – 3 band natural color):